Latest update of the Murtala Mohammed International Airport Rehabilitation, Lagos , Nigeria
GEORGE OLUWAFEMI SUNDAY
0:00 / 0:00
Latest update of the Murtala Mohammed International Airport Rehabilitation, Lagos , Nigeria
25 697 просмотров · 2 дн. назад
GEORGE OLUWAFEMI SUNDAY
4,81 тыс. подписчиков
25 697 просмотров · 2 дн. назад
Welcome back to another comprehensive site tour and progress update on the rehabilitation and expansion of the Murtala Muhammed International Airport (MMIA) in Lagos, Nigeria.
In this episode, we take a close look at the ongoing structural work across the terminal wings, hear directly from one of the site engineers, and check out nighttime progress on the arrival corridors.
In this video, we cover: • D-Wing & E-Wing Progress: Updates on roof steel structures, roof painting, sheet profile rolling on site, and ongoing glass facade installation. • Civil & Road Works: Concrete pouring for the retaining wall, backfilling, subgrade compaction, and expansion of the main arrival access road. • Solar System Infrastructure: A look at the specialized foundation setup designed for upcoming solar panel integration. • Engineer Insights: A conversation with site engineer Ibrahim Aliu Niko detailing the current phase and road connection works. • Terminal 2 Connection: Hand railing progress on the triangular link building bridging Terminal 1 and Terminal 2. • Nighttime Inspection: A look at lighting, nighttime truck deliveries, and traffic flow around the facility.
Timestamps: 00:00 - Introduction & Overview of MMIA Rehabilitation 00:57 - D-Wing Roofing & Glass Facade Progress 01:37 - Retaining Wall Concrete Pour (Interview with Engr. Ibrahim Aliu Niko) 02:35 - Arrival Area Expansion & Scaffolding Removal 03:05 - D-Wing Floor Concreting (C25 Concrete) 04:18 - E-Wing Extensions & Glass Fittings 04:55 - Roof Steel Painting & Solar Panel Foundation 06:03 - Local Workforce Impact & On-site Skills Development 07:02 - Update on the Landscaping Area 07:42 - Retaining Wall Base & Subgrade Preparations 08:26 - Terminal 1 & Terminal 2 Link Walkway 09:21 - On-site Roofing Sheet Profile Machine in Action 10:27 - Arrival Road Backfilling & Compaction Process 11:27 - Terminal 2 Entrance Extension 13:33 - Night View of MMIA, Street Lighting & Ongoing Deliveries 14:02 - Feedback from Lagosians on the Airport Transformation 15:12 - Wrap-up & Next Episode Preview
Join the Discussion: What part of the MMIA expansion are you most eager to see completed—the terminal interior, the solar installation, or the landscaping? Drop your thoughts in the comments below!
If you find these weekly infrastructure updates helpful, remember to like the video, share it, and subscribe to follow the full transformation journey.
#MurtalaMuhammedAirport #MMIA #LagosInfrastructure #LagosAirport #NigeriaProjects #AviationNigeria #GeorgeOluwafemiSunday