2026 October 5-9 | BYU's new Administration Building Construction
Brian Felt
0:00 / 0:00
2026 October 5-9 | BYU's new Administration Building Construction
134 просмотра · 12 дн. назад
Brian Felt
156 подписчиков
134 просмотра · 12 дн. назад
Updates this week:
Library Slant hole is almost filled; is tied in to the new building's sewer system.
West Wing roof is covered and looks structurally complete.
East Wing foundation is mostly complete.