Skouries – Operation «Sag Mill»: The project of transport and installing, at fast forward

HellasGold

0:00 / 0:00

Skouries – Operation «Sag Mill»: The project of transport and installing, at fast forward

5 974 просмотра · 11 лет назад
HellasGold
733 подписчика
5 974 просмотра · 11 лет назад
Step by step the whole process of transporting and installing the shell parts of the 1st Sag Mill at Skouries Flotation Plant. Watch the 6 sections of the operation that lasted months: maintenance, transport, base construction, hoisting, mounting and installing. And the major challenge of coordinating the team of experts from 7 companies, to implement the operation on time. http://www.hellas-gold.com/skouries