Mumbai Metro Line 9 is a 13.581 km extension of Metro Line 7, connecting Dahisar (East) and Mira-Bhayandar to the airport.
Key Project Details
• Total Length: 13.581 km (11.386 km elevated and 2.195 km underground)
• Total Stations: 10 stations
• Owner & Operator: Mumbai Metropolitan Region Development Authority (MMRDA)
• Project Base Cost: ₹6,607 Crore
• Rolling Stock: 8-coach trains with a capacity of 2,352 passengers
Route and Stations
The full line covers the following stations:
• Dahisar (East) to Mira-Bhayandar (Elevated):
1. Dahisar
2. Pandhurang Wadi
3. Miragaon
4. Kashigaon
5. Sai Baba Nagar
6. Meditiya Nagar
7. Shahid Bhagat Singh Garden (Maxus Mall)
8. Subhash Chandra Bose Stadium
• Andheri (East) to CSIA Extension:
1. Airport Colony (Elevated)
2. CSIA (Underground)
Operational Status & Timeline
• Phase I (Dahisar East to Kashigaon): Opened to the public on April 7, 2026 (covering ~4.7 km with 4 stations) via the MMRDA Metro Line 9 Overview.
• Phase II (Kashigaon to Subhash Chandra Bose Stadium): Expected to be completed and inspected by the CMRS around December 2026.
• Interchanges: Connects with Metro Line 7 (Red Line) and Metro Line 2A at Dahisar East, providing direct access towards Gundavali (Andheri East) and the wider Mumbai suburban network.