Clem decides to update his very old kitchen.
These were the activities on Days 22 and 25.
On Day 22, the electricians came back to install power points, three lights, and the electric oven. The plumber water installed pipe diversions for hot and cold water to make room for the exhaust ducting, and the sink with an inline water filter system.
The exhaust installers came back on Day 25 to finish installing the rangehood. The remaining built-in appliance, the coffee machine was installed by myself after making some ventilation holes in the cabinet niche and changing the electrical plug of the machine.
28 April and 01 May 2026