Slab formwork- deshuttering and Doka table shifting

My Daily Experiences

0:00 / 0:00

Slab formwork- deshuttering and Doka table shifting

14 540 просмотров · 4 года назад
My Daily Experiences
1,14 тыс. подписчиков
14 540 просмотров · 4 года назад
After 21 days Doka table form of slab are being shifted to 3rd floor . 1. 4 days slab cycle 2. Two floors below full slab support 3. third below floor are 50% proped .