FIDIC Yellow Book 2017 | Sub-Clause 1.3 Notices and Other Communications explained
Contract Management Channel
0:00 / 0:00
FIDIC Yellow Book 2017 | Sub-Clause 1.3 Notices and Other Communications explained
271 просмотр · 1 г. назад
Contract Management Channel
2,15 тыс. подписчиков
271 просмотр · 1 г. назад
In this video we read through Sub-Clause 1.3 to learn what the obligations are regarding Notices and other communications and we show how you can quickly draft a Notice with the help of Artificial Intelligence (AI) tools such as ChatGPT.
🌐 Visit CMC shop https://ko-fi.com/klinkerpublications...
🌐 For F2F FIDIC Training and contract management services visit https://aratis.nl/en/
Other Links
https://fidic.org
https://fidic.org/books/plant-and-des...
Notice example:
Subject: Notice under Sub-Clause 1.9 – Errors in the Employer’s Requirements
Dear [Engineer’s Name],
In accordance with Sub-Clause 1.9 [Errors in the Employer’s Requirements] of the Conditions of Contract for Plant and Design-Build (FIDIC Yellow Book, 2017 Edition), the Contractor hereby gives Notice that an error/defect/ambiguity/discrepancy has been identified in the Employer’s Requirements.
1. Description of the Issue:
The Contractor has identified the following matter:
[Provide a clear and specific description of the error, ambiguity, or discrepancy in the Employer’s Requirements, including reference to the relevant section, drawing, specification, or clause.]
2. Potential Impact:
This issue may affect:
The design and/or performance requirements of the Works;
The accuracy or completeness of the Contractor’s design;
The time required for completion of the Works; and/or
The Contract Price.
3. Contractor’s Action:
In accordance with Sub-Clause 1.9, the Contractor has not proceeded with any design or execution affected by the identified error and awaits the Engineer’s instruction or clarification.
. Request for Clarification/Instruction:
The Contractor respectfully requests the Engineer to review the above matter and to issue the necessary clarification, instruction, or revised Employer’s Requirement in accordance with Sub-Clause 1.9 and Sub-Clause 3.5 [Engineer’s Determinations], to avoid potential delay or disruption to the Works.
Please acknowledge receipt of this Notice in accordance with Sub-Clause 1.3 [Communications].
Yours faithfully,
For and on behalf of
[Contractor’s Company Name]
Signature: ___________________________
Name: [Authorized Representative’s Name]
Title: [Position/Designation]
Date: [Insert Date]
Optional Attachment (if applicable)
Annex 1: Extracts or marked-up drawings/specifications highlighting the identified error.
Annex 2: Preliminary assessment of potential impact (if prepared).