🏗️ How is one complete RCC floor constructed in just 7 days using Aluminium Formwork (Mivan Shuttering)?
Welcome to Part 3 of the Aluminium Formwork Series!
In this video, we will understand the complete 7 Days Working Cycle of Aluminium Formwork, from initial setting out to final concreting.
Using practical construction photographs, diagrams and explanations, I will take you through each day's activities and explain how different construction activities are coordinated to achieve a repetitive floor cycle.
What will you learn in this video?
DAY 01 – Setting Out & Wall Reinforcement
Setting out wall lines
Fixing and binding wall reinforcement
DAY 02 – Wall Formwork & Beam Bottom
Applying de-shuttering oil
Installing wall panels
Pin, wedge and wall tie connections
Fixing beam bottom
DAY 03 – Openings, Soffit & Props
Window opening panels
Soffit-length installation
Props and prop heads
Mid-beam and end-beam arrangements
DAY 04 – Deck Panels & Special Formwork
Deck panel installation
Room-wise panel coding
Staircase formwork
Kicker and corner components
DAY 05 – Slab Reinforcement
Bottom reinforcement
Top reinforcement
Binding and cover spacers
DAY 06 – Final Checking / Pre-Pour Inspection
Wall alignment and verticality
Slab level and dimensions
Panel connections and wall ties
Props and reinforcement
MEP services and openings
DAY 07 – Concreting
Concrete supply and pumping
Wall and slab concreting
Compaction and vibration
Finishing and curing
🎯 Why watch this video?
✅ Understand the complete aluminium formwork sequence.
✅ Learn day-wise construction activities.
✅ Understand the coordination between formwork, reinforcement and MEP services.
✅ Learn important site inspection points.
✅ Understand repetitive floor planning and construction cycle management.
🎓 Who should watch?
Civil Engineering Students
NICMAR Students
Site Engineers
Planning Engineers
Project Engineers
Construction Professionals
📌 Previous Videos:
Part 1 – Introduction to Aluminium Formwork
Part 2 – Understanding Aluminium Formwork Components
If you find this video useful, please LIKE, SHARE and SUBSCRIBE!
BUILT SMART WITH JAY
Learn Construction Practically, One Activity at a Time.
🔖 Hashtags
#aluminiumformwork #mivanshuttering #mivanconstruction #7DaysWorkingCycle #constructionprocess #CivilEngineering #ConstructionEngineering #SiteEngineer #planningengineer #nicmar #rccconstruction #buildingconstruction #FormworkTechnology #constructionplanning #BuiltSmartWithJay