Maintenance backlog calculation by trade with a worked example

ManWinWin - Maintenance Software CMMS

0:00 / 0:00

Maintenance backlog calculation by trade with a worked example

12 просмотров · 3 дня назад
ManWinWin - Maintenance Software CMMS
1,43 тыс. подписчиков
12 просмотров · 3 дня назад
A maintenance backlog calculation divides outstanding labour hours by the weekly capacity available to perform that same work. Calculate it separately for each trade and distinguish ready work from blocked work. This reveals constraints that a single work order count, or a combined crew figure, can hide.