Lecture 2- Critical path method (CPM)
NirmanVeda@RM
0:00 / 0:00
Lecture 2- Critical path method (CPM)
135 просмотров · 3 нед. назад
NirmanVeda@RM
147 подписчиков
135 просмотров · 3 нед. назад
Lecture 2: Critical Path Network - From Work Plan to Control Model
In this lecture, we will convert Project Inputs (WBS, activity list, durations, logic) into a complete CPM Network.
Topic Covered:
1. Construct CPM Network using AON / AOA
2. Run Time Analysis: Forward Pass (ES/EF) and Backward Pass (LS/LF)
3. Calculate Float: TF = LS-ES = LF-EF. If TF=0 = Critical Activity
4. Identify Critical Path: Longest path which controls project finish. Any delay on it delays the whole project.
5. Test, Update & Control Cycle: How to use CPM for real site control
6. Calendarization with Example Project Duration
Outcome: A testable control model with current forecast, float, and completion priorities.