AK912 Discharge of 2 x 186te Transformers

Allelys

0:00 / 0:00

AK912 Discharge of 2 x 186te Transformers

4 252 просмотра · 1 дн. назад
Allelys
4,2 тыс. подписчиков
4 252 просмотра · 1 дн. назад
A closer look at the discharge of two 186te transformers for the Eggborough BESS project, where the AK912 lifted both units at a 62m radius. To comply with environment restrictions, a solution was designed to introduce spacer pontoons, which removed the need for dredging. The discharge formed part of our wider project scope to receive, transport and install both transformers.