SUMMARY
Cement
= 121 bag x ₱235 = ₱28,435
Hollow blocks;
1086pcs x ₱ 15
= ₱ 16,290
Sand
=9.5m³ x ₱950/m³ = ₱9,025
Gravel
=9m³ x ₱1,200 = ₱10,800
REBAR;
12mm 42pcs x ₱ 220
=₱9,240
10mm 14pcs x ₱ 140
=₱1,950
9mm x 112pcs x ₱95
= ₱ 10,640
FORM WORKS;
= ₱15,OOO
TOTAL MATERIALS for
STRUCTURE ; = ₱ 101,380
TRUSSES ROOFING = ₱ 75,000
TOTAL = ₱ 176,380
LABOR = 80k to 90k