In the 1930s, engineers building Hoover Dam faced a problem nobody could see: the concrete was cooking itself from the inside. Poured as one solid mass, the dam would have taken more than a century to cool, and it would have cracked long before.
This is how they solved it: a river moved into four tunnels, high scalers hanging from ropes, a dam split into hundreds of columns poured five feet at a time, more than 580 miles of cooling pipe, a refrigeration plant that could make a thousand tons of ice a day, and the grout that sealed it all back into one wall. And why, ninety years later, it is still standing.
00:00 The ice was for the wall
00:37 Why this dam should not exist
01:34 A river that did what it wanted
04:15 Moving the Colorado
07:28 The hidden heat
11:25 The shape that holds the lake
13:49 The price
14:32 Why it is still standing
Sources:
U.S. Bureau of Reclamation, "Hoover Dam FAQs" and "The Story of Hoover Dam"
essays (concrete; high scalers).
National Park Service, "The Greatest Dam in the World: Building Hoover Dam"
(Teaching with Historic Places).
American Society of Civil Engineers, Hoover Dam Historic Civil Engineering
Landmark.
Music (YouTube Audio Library):
"At the Precipice of a Dying Light" by Dan Bodan
"Final Girl" by Jeremy Blake
"Your Suggestions" by Unicorn Heads